The New Project Of Mojia Biotech (Guang An) Limited For Vb5 Will Begin To Produce in The First Half Of 2022.
2022-04-13
The biotechnology industrialization project of Mojia Biotech(Guang an)Limited. has been under construction for more than 3 years. Recently, it has been reported that the project may be put into production in the first half of 2022. At present, relevant projects have been completed, and relevant trial production and certification are being prepared.
List of project product plans:
PRODUCT NAME | ANNUAL PRODUCTION(T/A) | PACKING | PRODUCTS TO |
D- Calcium Pantothenate | 5000 | BAGS | SALES |
D-Panthenol | 3000 | BARRELS | SALES |
L-Alanine | 5000 | BAGS | SALES |
L- Aparaginic acid | 5000 | BAGS | MAINLY SELF USE |
Beta-Alanine | 2100 | BAGS | MAINLY SELF USE |
Zymin | 3000 | BARRELS | MAINLY SELF USE |
Adenine | 300 | BAGS | SALES |
D-Ribose | 300 | BAGS | SALES |